Griffin Substation Design

Country:

Australia

Client:

Jemena Asset Management

Sector:

Hydropower and Energy
Image Gallery
The project involved the construction of a 110/33kV bulk supply substation, situated in a sensitive low-lying wetlands area containing acid sulphate soils. The design services for the project included site access, earthworks, drainage and hydraulics, road works, fence enclosure, structural foundations for electrical plant items including control building and transformer, supply and installation of electrical conduits. SMEC’s services included: delivery of the 'Issue For Construction' civil design package including drawings and specification and local council approvals, preparation of flood studies, geotechnical review, design and drafting of structural foundations, earthworks, road works, fence enclosure, stormwater and water and sewerage systems.