Construction innovation and delivery milestones
The WTP has achieved key delivery milestones, including the completion of all tunnel boring machine (TBM) excavation between Sydney Olympic Park and Westmead.
At Clyde, the project has achieved a world-first application of a custom-designed Lining Erector Machine (LEM) to install precast segmental linings within mined spur tunnels connecting the mainline tunnels to the SMF. This approach, inspired by TBM technology, replaced traditional cast-in-situ lining methods, improving construction efficiency, safety and quality while delivering a watertight finish comparable to TBM-constructed tunnels.
Segments were manufactured locally at the project’s Eastern Creek precast facility, supporting program certainty and sustainability outcomes.
Improving community outcomes
As part of Sydney Metro West, the WTP provides significant benefits to the Parramatta area and has been constructed with minimal impact to local communities and surface infrastructure.
The metro network is supported by the SMF, which will serve as the operational base for the state-of-the-art driverless system.
To improve connectivity while minimising disruption, the team developed an alternative access road alignment, including an overpass bridge over the railway line into the Clyde facility. This reduced the need for complex interface works with existing infrastructure and helped manage traffic impacts during construction.
Alternative tunnelling alignment
The spur tunnels were strategically constructed beneath an existing 100-year-old sewer main at Clyde, maintaining a minimum one metre separation between the two assets. By tunnelling below the pipeline rather than diverting it, the project saved approximately six months of construction time and avoided relocation of the sewer.
Comprehensive 3D structural analysis was undertaken to model the alignment of both the sewer and the proposed tunnels, establishing the interaction zone between the two assets. In accordance with stringent authority design guidelines, the team demonstrated that the tunnels could be constructed safely while maintaining required clearances and keeping impacts within acceptable limits.
These tunnels were successfully excavated beneath the operational sewer. A custom LEM was then used to install precast segmental linings, replacing traditional cast-in-situ lining methods and improving efficiency, safety and quality. Tunnel segments were manufactured at the Eastern Creek facility, supporting both program certainty and sustainability outcomes.
Reduction in length of the Clyde Dive Structure
The geotechnical and structural team worked together to optimise the dive structure design. This reduced excavation volumes, removed the need for tension piles, and minimised perimeter piling.
The portal structure was also designed to integrate a services building within the footprint, reducing the overall length by approximately 60 metres without altering the alignment.
This reconfiguration delivered substantial material savings, reduced the surface footprint, and improved both sustainability and constructability results.
Permanent solution for temporary works – Parramatta metro station
The team identified an opportunity to replace a temporary pile retention system with a diaphragm wall as a permanent solution. This innovation reduced concrete quantities and improved sustainability by minimising materials that would otherwise become redundant following completion of the station box excavation.