SMEC collaborated with Port of Townsville Limited (the Port) on the Channel Upgrade project, a major project which has increased capacity of the existing shipping channel. As the largest general cargo and container port in Northern Australia, the Port of Townsville is essential infrastructure, pivotal to the economic development of the region.

At its narrowest, the shipping channel was only 92 metres wide, making it one of the most constrained in the country. Through dredging activities, the project has increased the width along the approach channel to accommodate larger vessels. The channel width now ranges from approximately 180m at the port entrance to 120 metres at the seaward end.

Material re-use creates benefits for all

SMEC was engaged to undertake the detailed design of the rock bund wall, a structure that has been used to safely accommodate the dredged material from the channel widening. The Port has re-used the dredged material produced by the Channel Upgrade project works to form a land reclamation area, which will eventually form part of the outer harbour, in line with the Port’s long-term development plan.

Dredging has recently been completed, with all dredged material successfully placed within the rock bund wall reclamation area. The Channel Upgrade project will be complete by the end of 2024, allowing cruise, commercial and defense vessels up to 300m in length to safely navigate to the Port of Townsville. This will be a significant contribution to the future growth and economic potential of the region.


Figure 1 – Channel Upgrade Project Summary

The rock wall bund is currently constructed to an intermediate stage which enabled the dredge material to be placed within the reclamation area. Now that the dredge material has been placed, the remainder of the rock bund wall can be constructed, which comprises rock protection at the rear of the structure. The rock protection works consist of additional layers of large rock, providing additional stability against the impact of high tides and waves generated during cyclones.  A summary of key design highlights is provided in the physical model photographs below.


Figure 2 – Intermediate Bund Physical Model


Figure 3: Rear Crest Protection Structure Physical Model

Modelling for risk mitigation

Townsville is located within an active cyclone region, requiring the design of the land reclamation area to withstand significant tides and waves generated during extreme weather events.

As part of the design process, SMEC’s team of coastal engineering specialists adopted a holistic and risk-based approach with the aid of numerical and physical modelling, to support a design which meets contemporary guidelines and standards.

The numerical and physical modelling allowed coastal processes to be simulated, with cyclonic wind field forcing and the propagation of swell through the reef to be modelled in detail.


Figure 4 – WAMGBR model peak Hs wave penetration during TC Yasi (MOS Solutions SEA, 2019)

Numerical modelling was undertaken by Met Ocean Solutions Ltd and Systems Engineering Australia (SEA) Pty Ltd, simulating the impact of cyclonic winds from the Pacific Ocean and through the Great Barrier Reef. The numerical modelling confirmed the known phenomena within the Port where short wind generated waves combine with long period swell waves which travel through the submerged Great Barrier Reef structures.

Our team worked with the Water Research Laboratory at the University of New South Wales to undertake physical modelling, enabling coastal processes to be reproduced, complex wave interactions to be modelled and the performance of the rock wall bund to be assessed.

Our physical modelling approach allowed specific processes to be investigated in detail, thereby informing our bund design, as follows:

  • A 2D flume model was used to investigate and optimise rock sizes for the bund under breaking waves;
  • 3D large basin modelling was undertaken to investigate the how waves move spatially and the interaction of incoming waves and the channel. Wave refraction, reflection, diffraction and wave concentrations along the channel were observed and measured, identifying increases in wave height by up to 50% under specific conditions, when compared to what was modelled numerically in some locations;
  • Additional 3D modelling within a flume to specifically model the rock bund wall corner (termed ‘quasi 3D’), was then undertaken to confirm rock stability based on the increased wave heights identified in the 3D large basin;
  • Additional 2D flume modelling to confirm rock stability and geometry of the rear crest protection structure when exposed to the increased wave heights identified within the 3D large basin.

Anthony Folan will be presenting some of the key learnings from this project to industry at the next available opportunity.

Undertaking a holistic numerical and physical modelling process provided greater design accuracy, through a better understanding of coastal processes, resulting in a reduction in whole of life costs for the rock bund wall structure.
———— Anthony Folan, Senior Associate Coastal & Maritime Engineer
Photos courtesy of The Port of Townsville.